Terminal Pulogebang Belum Bisa Dioperasikan Maksimal

Incomplete JORR Construction Disturbs Pulogebang Terminal

Pulogebang Bus Terminal, East Jakarta is still can not operate maximally since the road access construction of Jakarta Outer Ring Road (JORR) is yet unfinished. The operational permit from Ministry of Transportation is also postponed.

The terminal is ready to operate, but we need road access

Nurhayati Sinaga, Head of Pulogebang Terminal UPT, said that the permit is yet issued, while her side had proposed since 2015. She hoped Bina Marga Department will finish the road access development.

“The terminal is ready to operate, but we need road access. That is why the permit is not issued by the ministry,” she said.

Tanjung Priok Terminal Cleaned

If the terminal is operated for big bus, then the alternative road will be in terrible traffic jam.

Meanwhile, Yusmada Faizal, Jakarta Head Dept. of Bina Marga, admitted that the road access from terminal to JORR is finished, but the access from JORR to terminal is delayed.

“We face a land lawsuit precisely beside the toll road. Construction target is to finish in March,” he stated.

Linked News
Popular News indeks
  1. Volcanic Ash Reaches Jakarta, Health Agency Calls for Protective Measures

    access_time06-09-2026 remove_red_eye1609 personBudhi Firmansyah Surapati
  2. Jakartans Urged to Stay Calm and Take Precautions Amid Mt. Anak Krakatau Volcanic Ash

    access_time06-09-2026 remove_red_eye804 personBudhi Firmansyah Surapati
  3. Jakarta Provincial Government Anticipates the Impact of Volcanic Ash from Mount Anak Krakatau

    access_time06-09-2026 remove_red_eye661 personFolmer
  4. Jakarta BPBD Urges Residents to Prepare for Meteorological Drought

    access_time04-09-2026 remove_red_eye571 personAldi Geri Lumban Tobing
  5. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye564 personFakhrizal Fakhri